PROJECT NAME |
CLIENT / PURCHASER |
LOCATION |
DESCRIPTION |
VENDOR SCOPE |
YEAR |
REMARKS |
MANUFACTURER/ SUPPLIER |
| SABIYA ¥² DISTILLATION PLANTS |
Ministry of energy KUWAIT Doosan Heavy Inds. & const. |
K SITE KUWAIT |
Chemical Dosing system |
Turn-Key (Skid Base) |
2006.09 |
Storage tank : 27 set Injection Pump : 28 sets Piping on base plate : 16 set |
SYSCO CO., LTD /OEM |
| SIPAT SUPER THERMAL POWER PJT STAGE - ¥° |
NTPC Doosan Heavy Inds. & const. |
SIPAT INDIA |
Chemical Cleaning Facility |
Turn-Key (Skid Base) |
2007.7 |
Storage tank : 8 sets Injection Pump : 8 sets Piping on base plate : 4 sets |
SYSCO CO., LTD /OEM |
| SABIYA DISTILLATION PLANTS |
Ministry of energy KUWAIT Doosan Heavy Inds. & const. |
K SITE KUWAITE |
Acid Cleaning System |
Turn-Key (Skid Base) |
2005.09 |
Storage tank : 2 sets Injection Pump : 2 sets Piping on base plate : 1 set |
SYSCO CO., LTD /OEM |
| REHAB POWER STATION |
CEGCO Doosan Heavy Inds. & const. |
Irbid Jordan |
Chemical Dosing system (For Power Plant) |
Turn-Key (Skid Base) |
2004.10. |
Storage tank : 5 sets Injection Pump : 14 sets Piping on base plate : 5 sets |
SYSCO CO., LTD /OEM |
| FUJAIRAH WATER & POWER PLANTS |
U.O.G Doosan Heavy Inds. & const. |
Fujairah U.A.E |
Chemical Dosing system (For Desalination Plant) |
Turn-Key (Skid Base) |
2002.3 |
Storage tank : 30 sets Injection Pump : 30 sets Barrel pump : 6 sets Piping on base plate :15 sets Piping on base plate : 2 set |
SYSCO CO., LTD /OEM |
| UMMAL NAR DESAL PJT. STATION 'B' |
Adewa Doosan Heavy Inds. & const. |
Ummal nar, U.A.E |
Chemical Dosing system |
Turn-Key (Skid Base) |
2001.1 |
Solution Tank : 2 Set Injection Pump : 2 Set Agitator : 2 set |
SYSCO CO., LTD /OEM |
| AL-TAWEELAH A2 POWER & DESAL. |
Emirates CMS Power Co. Dosan Heavy Inds. & const. |
Al-taweelah, U.A.E |
Acid Cleaning System |
Tum-Key (Skid Base) |
1999.10 |
Storage tank (35 §© ): 1 set Dilution Tank (20 §© ) : 1set cleaning tank : 2 set feed pump : 4 set Piping on base plate : 2Set |
SYSCO CO., LTD /OEM |
| AZ-ZOUR Ph3 DESALINATION PJT |
MINISTRY OF ELECTRICITY / KOREA HEAVY INDS. & CONST. |
KUWAIT |
Acid Cleaning System |
Tum-Key (Skid Base) |
1999.10 |
Storage tank : 2 set Injection Pump : 2 Set Sump pump : 1 set Piping on base plate : 1Set |
SYSCO CO., LTD /OEM |